A First for Turkey
15 October 2018
Waste heat recovery in Turkish cement production is a very dynamic and promising market; many cement plants have already implemented waste heat recovery (WHR) systems. Since 2011, a total of 12 WHR plants have been commissioned, with an overall installed capacity of about 120 MW. At the beginning of 2018, Çimko (a Sanko Group company) selected CTP Team as its EPC contractor, and Turboden as its Organic Rankine Cycle (ORC) and air-cooled condenser supplier. This is all for its site in Narli, Karamara, which will be the first project in Turkey based on ORC technology, and will include a thermal oil loop for heat recovery.
SUBSCRIBE TO OUR NEWSLETTER
Get all the news, discover our technologies and find out about our latest developments.
REGISTER HERE